| Task |
Activity |
Finish Date |
| 1 |
Refine workplan |
7/09/07 |
| 2 |
Establish project working group |
7/09/07 |
| 3 |
Develop WSUD Strategies for case studies in suitable format for communication and identify case studies for sub-catchment scale application of WSUD treatment train |
2/11/07 |
| 4 |
Identify potential WSUD objectives for Darwin |
2/11/07 |
| 5 |
Critical Analysis of WSUD/Stormwater Treatment Options for Darwin |
2/11/07 |
| 6 |
Prepare a stakeholder communication and consultation strategy (including establish website, fact sheets, presentations) |
10/12/07 |
| 7 |
Prepare and communicate a definition of WSUD within Darwin |
10/12/07 |
| 8 |
Review and report on policy, programme, technical and decision-support systems for WSUD in Australia (including any barriers to uptake of WSUD and respective jurisdictional responses) |
10/12/07 |
| 9 |
Identify potential barriers to uptake of WSUD in the NT. Develop strategy to address barriers |
10/12/07 |
| 10 |
Develop WSUD Strategies for case studies in suitable format for communication and identify case studies for sub-catchment scale application of WSUD treatment train |
18/01/08 |
| 11 |
Prepare detailed workplan for development of NT WSUD policy, objectives, design manual, performance standards and decision-support tools |
18/01/08 |
| 12 |
Prepare draft NT WSUD policy and objectives for Darwin including understanding existing legislation, workshops etc. |
28/04/08 |
| 13 |
Assess application of WSUD objectives and management practice options across a range of development situations and/or catchment-scale treatment-train & confirm set of objectives |
28/04/08 |
| 14 |
Undertake consultation of draft WSUD policy and WSUD objectives to stakeholders and barriers to WSUD |
28/04/08 |
| 15 |
Define requirements of WSUD Guidelines and Tools |
15/05/08 |
| 16a |
Document Draft WSUD Guidelines and Tools in including High Level and Conceptual Design Guideline and Conceptual Design Tools (MUSIC Guidelines) |
2/06/08 |
| 16b |
Document Draft WSUD Guidelines and Tools in including Technical Design Guideline and Technical Design Tools (Deemed to Comply Solutions, Standard Drawings etc. |
16/08/08 |
| 17 |
Prepare Draft WSUD decision support tools for Darwin Harbour, consistent with WQPP, linking policy, objectives and guidelines |
16/08/08 |
| 18 |
Undertake stakeholder consultation of WSUD Policy, WSUD design manual and performance standards, and decision support Tools and seek approval |
19/10/08 |
| 19 |
Finalise WSUD design manual, decision support tools and performance standards |
19/12/08 |
| 20 |
Seek NT Government approval for WSUD Policy, WSUD design manual and performance standards and decision support tools |
19/12/08 |
| 21 |
Develop and publish stormwater management plans for key subcatchment in Darwin to illustrate application of WSUD Policy/Framework, design manual and decision support tools |
19/12/08 |
| 22 |
Develop an implementation strategy for incorporating policies and provisions for WSUD within NT planning policies, strategic plans and development approval processes as well as local government instruments |
13/03/09 |
| 23 |
Ongoing communication and website management |
13/03/09 |
| 24 |
Capacity Building and Training including government, local authorities, developers and industry practitioners |
13/03/09 |
| 25 |
Incorporate policies and provisions for WSUD into NT government planning policies, strategic plans and development approval processes, as well as relevant local government instruments. Implement agreed strategy to address barriers to uptake of WSUD |
8/05/09 |